Coal

C MINE STRIP - UPPER FREEPORT

  • Location Garrett County, MD
  • Approx. Value $18,500,000
  • Client Mettiki Coal Company
  • Status In Progress

Project Description

Everson was tasked with taking over for a floundering company who could neither make the project profitable nor meet the coal shipment demand.

The customer handed down a strict deadline and a coal quota, which required Everson to move a minimum of 300,000 cy of material per month, in tight quarters, then split, load, and ship up to 20,000 tons per month. This quota was expertly achieved through a combination of our personnel, equipment, and supervision. Project consisted of 600,000 tons.